What is an asbestos demolition survey?
An asbestos demolition survey is a fully intrusive survey intended to locate and identify all asbestos-containing materials, so far as reasonably practicable, throughout a building or structure before demolition begins.
Because demolition will disturb the complete building fabric, the survey must examine concealed areas that may not have been accessed during previous management or refurbishment surveys. This can include wall cavities, floor voids, roof spaces, service risers, ducts, plant rooms and structural enclosures.
Is an asbestos demolition survey a legal requirement?
Before demolition or other work that could expose employees to asbestos begins, the employer must identify whether asbestos is present and, where it is present, determine its type and condition. Regulation 5 of the Control of Asbestos Regulations 2012 specifically applies to demolition, maintenance and other work liable to disturb asbestos.
A suitable demolition survey is normally the practical means of obtaining this information for a building scheduled for complete demolition.
When is a demolition survey required?
A demolition survey should be completed before the complete demolition of a building or structure where asbestos may be present.
This may include:
- Houses and blocks of flats
- Commercial premises
- Schools and public buildings
- Factories and warehouses
- Garages and outbuildings
- Boiler houses and plant rooms
- Agricultural or industrial structures
- Ancillary buildings within a redevelopment site
For buildings constructed or refurbished before 2000, asbestos should be presumed possible unless reliable evidence demonstrates otherwise. HSE also notes that older plant or equipment may contain asbestos even where the surrounding building is more recent.
How is a demolition survey different from a refurbishment survey?
Both surveys are intrusive, but their scope and purpose are different.
A refurbishment survey is restricted to the areas and building elements affected by clearly defined refurbishment works.
A demolition survey covers the whole building or structure scheduled for demolition because the complete fabric will ultimately be disturbed.
For example, a refurbishment survey for replacing windows may focus on window surrounds, panels, reveals and adjacent finishes. A demolition survey of the same property would need to investigate the entire structure, including areas unrelated to the windows.
HSE groups refurbishment and demolition surveys together as intrusive surveys used to identify hidden asbestos before work begins, but the inspection scope must reflect the proposed works.
Can a management survey be used for demolition?
No. A management survey is intended to support the normal occupation, use and routine maintenance of a building. It is not normally sufficiently intrusive to identify all asbestos that could be disturbed during demolition.
Existing management survey information can assist with planning, but it should not be treated as a substitute for a demolition survey.
Can a previous refurbishment survey be used for demolition?
Usually not, unless the earlier survey demonstrably covered the entire building to the level required for complete demolition.
Most refurbishment surveys are limited to a particular project or defined work area. Areas outside that scope may not have been intrusively inspected. The previous report should therefore be reviewed carefully against the current demolition boundary before it is relied upon.
Is a demolition survey destructive?
Yes. A demolition survey is normally the most intrusive form of asbestos survey.
It may require controlled damage to:
- Walls and partitions
- Ceilings
- Floors
- Boxing and risers
- Fixed panels
- Roof and service voids
- Structural enclosures
- Redundant plant
This is necessary because asbestos may be concealed within the building fabric. HSG264 covers the planning, execution and reporting of asbestos surveys, including intrusive surveys undertaken before demolition.
Can the building remain occupied during the survey?
The areas being intrusively surveyed should normally be vacant and effectively segregated.
Demolition surveys may involve substantial disturbance, opening of building elements and temporary debris. HSE guidance indicates that intrusive refurbishment or demolition survey areas should be unoccupied, isolated from other parts of the property and cleared or suitably protected.
Where only part of a larger site is being surveyed, other areas may sometimes remain operational where a suitable risk assessment and robust segregation arrangements are in place.
Does all asbestos have to be removed before demolition begins?
Asbestos-containing materials should normally be removed before demolition reaches or disturbs them.
The required removal method will depend on the material, condition, extent and likely fibre release. Some work may be non-licensed, while higher-risk work must be undertaken by an HSE-licensed asbestos removal contractor.
The demolition survey identifies the materials present; it does not itself authorise demolition through asbestos-containing elements.
Who is responsible for arranging the demolition survey?
Responsibility will usually sit with the client, building owner, dutyholder or organisation controlling the demolition project.
Under the Construction (Design and Management) Regulations, relevant asbestos information should also form part of the pre-construction information provided to designers and contractors. Contractual responsibility should be agreed early, but transferring the task does not remove the need to ensure suitable information is available before work starts.
Who should carry out an asbestos demolition survey?
The survey should be completed by a competent asbestos surveyor or surveying organisation with appropriate training, knowledge, experience and quality-management arrangements.
HSE advises those appointing asbestos professionals to check competence and ensure surveying work is undertaken in accordance with recognised guidance such as HSG264.
Does the survey cover garages, shed and outbuildings?
Only when they are clearly included within the agreed survey scope.
Ancillary structures are frequently overlooked during redevelopment planning. The client should identify every structure within the demolition boundary, including garages, sheds, stores, plant rooms, canopies, compounds and detached service buildings.
Any structure omitted from the original scope may require a further survey before it is demolished.
Are underground chambers and ducts included?
They should be considered where they form part of the demolition works and can be accessed safely.
Access may depend on confined-space controls, service isolation, structural safety and specialist assistance. Where an area cannot be accessed, the limitation must be clearly recorded and resolved before demolition disturbs it.
What happens if part of the building cannot be accessed?
The inaccessible area should be clearly identified in the report, together with the reason access was not achieved.
It should not simply be assumed asbestos-free. Depending on the circumstances, the area may need to be presumed to contain asbestos or inspected through a supplementary survey once safe access has been arranged.
Demolition should not proceed into an unassessed area without an appropriate risk assessment and resolution of the outstanding asbestos information.
What information should be provided before the survey?
The surveyor should be given as much relevant project information as possible, including:
- Site and floor plans
- The complete demolition boundary
- Previous asbestos reports
- Structural information
- Known access restrictions
- Details of underground or ancillary structures
- Service-isolation arrangements
- Demolition sequence or methodology
- Information about hazardous or unstable areas
Accurate information helps ensure the survey is properly planned and that no buildings or structural elements are unintentionally excluded.
Does the electricity, gas and water need to be isolated?
Services should be assessed before intrusive inspection begins, and isolation may be necessary where the surveyor could encounter live electrical systems, gas supplies, pressurised pipework or operational plant.
The precise requirements depend on the property and intended inspection. Isolation should be completed and confirmed by competent persons rather than assumed.
How long does a demolition survey take?
The duration depends on:
- The building's size and construction
- The number of structures included
- Its condition and stability
- The complexity of plant and services
- Access arrangements
- The extent of intrusive inspection
- The number of samples required
A small garage may take only a limited period, whereas a multi-storey commercial or industrial site may require several days or a phased programme.
How quickly will the report be available?
The report can normally be completed once the inspection and laboratory analysis are finished.
Timescales depend on the number of samples, laboratory turnaround and the complexity of the findings. Where demolition programmes are time-sensitive, this should be discussed before instruction so inspection, analysis and reporting can be planned appropriately.
Demolition should not start merely because the site inspection has taken place; the completed findings must first be reviewed and acted upon.
What will the demolition survey report include?
A comprehensive report will typically include:
- The agreed survey scope
- Survey methodology
- Executive summary
- Asbestos register
- Material and sample assessments
- Photographs
- Annotated plans
- Laboratory results
- Areas not accessed
- Limitations and exclusions
- Recommendations for removal or further investigation
The report should provide clear information that can be incorporated into asbestos-removal planning and the wider demolition programme.
Does the survey include asbestos removal?
No. The demolition survey identifies asbestos-containing materials and provides recommendations.
Removal is a separate activity requiring its own assessment, plan of work, appropriately trained personnel and, for licensable materials, an HSE-licensed asbestos removal contractor.
Strata can help clients interpret the findings, define removal requirements and coordinate the next stage of the project where required.
What happens if asbestos is discovered after demolition starts?
Work should stop immediately in the affected area, access should be restricted and the material left undisturbed.
A competent asbestos professional should assess the situation and determine whether sampling, specialist cleaning, air monitoring or licensed removal is required. Demolition should not recommence in the affected area until the asbestos risk has been properly controlled.
Unexpected discoveries often indicate that the original survey scope, access or demolition boundary should also be reviewed.
Do domestic properties require demolition surveys?
The specific duty to manage under Regulation 4 does not apply inside a private domestic residence. However, employers and contractors still have duties when their work may expose workers or others to asbestos.
Therefore, where a pre-2000 domestic property is being demolished, suitable asbestos information is still required before contractors disturb the structure. HSE confirms that the domestic exemption from the duty to manage does not remove the wider requirements controlling work with asbestos.
Can asbestos be identified by appearance alone?
No. Some materials may be strongly suspected based on their age, appearance and use, but visual inspection alone cannot reliably confirm whether asbestos is present.
Representative samples should normally be analysed by a competent laboratory. Where sampling is unsafe or impossible, the material may need to be presumed asbestos-containing until proven otherwise.
Why should the survey be arranged early?
Commissioning the survey early allows time to:
- Review and act upon the findings
- Obtain asbestos-removal quotations
- Appoint appropriately licensed contractors
- Complete notification periods where applicable
- Programme removal before demolition
- Arrange waste disposal
- Address inaccessible areas
- Avoid delaying the demolition contractor
Early asbestos planning is generally far less disruptive and expensive than responding to an unexpected discovery after demolition has started.
Related Asbestos Services:
Asbestos Management Surveys:
An asbestos management survey is designed to locate, as far as reasonably practicable, the presence and extent of asbestos-containing materials within occupied buildings. The survey helps dutyholders comply with the Control of Asbestos Regulations 2012 by providing an asbestos register and information required to safely manage asbestos during normal occupation and routine maintenance.
Learn more about our Asbestos Management Surveys →
Refurbishment Asbestos Surveys:
If refurbishment or alteration works are planned, a refurbishment asbestos survey should be completed before work begins. These intrusive surveys identify asbestos-containing materials likely to be disturbed during the proposed works, helping protect contractors and ensuring compliance with current legislation.
Learn more about our Refurbishment Asbestos Surveys →
Asbestos Re-Inspection Surveys:
Known or presumed asbestos-containing materials should be periodically inspected to confirm they remain in a satisfactory condition. Our asbestos re-inspection surveys update your asbestos register and help ensure asbestos continues to be managed safely.
Learn more about our Asbestos Re-Inspection Surveys →
Asbestos Sampling & Testing:
If you're unsure whether a material contains asbestos, representative samples can be safely taken and submitted to a UKAS-accredited laboratory for analysis. Sampling provides certainty before refurbishment, demolition or maintenance works commence.
Learn more about Asbestos Sampling & Testing →
Asbestos Management Plans:
An asbestos management plan provides the practical arrangements required to manage asbestos safely within non-domestic premises. It supports dutyholders in meeting their legal responsibilities by detailing inspection frequencies, communication procedures and emergency arrangements.
Learn more about Asbestos Management Plans →
Asbestos Waste Collection & Disposal:
Following asbestos removal works, waste should be transported and disposed of in accordance with current hazardous waste legislation. We provide compliant asbestos waste collection and disposal services for domestic, commercial and industrial clients throughout the UK.
Learn more about Asbestos Waste Collection & Disposal →
Non-Licensed Asbestos Removal:
Certain lower-risk asbestos-containing materials can be removed without the need for a licensed asbestos contractor, provided the work falls within the scope of non-licensed or notifiable non-licensed work. We undertake selected non-licensed asbestos removal works in accordance with current legislation and industry guidance.
Learn more about Non-Licensed Asbestos Removal →
Asbestos Consultancy:
Our independent asbestos consultancy service provides practical advice on asbestos legislation, refurbishment planning, management arrangements, contractor support and compliance. Whether you require technical guidance or ongoing consultancy support, we're here to help.
Learn more about Asbestos Consultancy →
Return to Home Page